  1. North Carolina regulators set a data-centre rate schedule for Duke Energy, with a stranded-generation charge

    On 16 Nov 2026 the North Carolina Utilities Commission approved Duke Energy Carolinas' rate settlement without modification, except the large-load tariff settlement filed on 6 Oct 2026, according to Duke's Form 8-K (Exhibit 99.1). The order also establishes a DC Schedule for data-centre customers. The 8-K lists a minimum 15-year contract for data centres above 100 MW, minimum billing at 75% of contract demand, a letter of credit for transmission network upgrades and a stranded-generation charge. Duke's release dated 17 Nov 2026 says the schedule applies to loads above 50 MW and that new rates take effect Jan. 1. Why it matters to the watch: the order sets contract, billing and stranded-generation terms for data-centre power, the grid load behind AI compute.

    Source published
    16 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    17 Nov 2026, 3:46 p.m. ET
    Location precision
    Region level (approximate)
  2. Spain may approve decree requiring data centres to source 80% of electricity from renewables, matched hour by hour

    On 17 November 2026 CNBC reported that Pedro Sánchez's cabinet could approve a decree on Tuesday. The proposed rules would "require 80% of electricity used by data centers to come from renewable sources matched hour by hour", with "projects potentially losing grid access if they fail to comply". The industry group SpainDC says the rules could put 80% to 90% of investment at risk, and its president, Emilio Díaz, says the group will use "all the institutional, regulatory and legal avenues at our disposal". Whether the cabinet approved the decree, and the final text, were not confirmed when this was recorded. Why it matters to the watch: the proposed rules would require 80% of data-centre electricity to come from renewables matched hour by hour, with projects potentially losing grid access if they fail to comply.

    Source
    CNBC (opens in a new tab) and 1 more
    Source published
    16 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    17 Nov 2026, 10:47 a.m. ET
    Location precision
    Country level (approximate)
  3. Quaise Energy signs 50 MW geothermal power deal with Google for three data centres in The Dalles, Oregon, starting as early as 2030

    On 17 Nov 2026 Quaise Energy announced a 50 MW geothermal power purchase agreement with Google. Quaise's press-release index lists the release as 'Quaise Energy Signs 50 MW Geothermal Power Purchase Agreement with Google', dated Nov. 17, 2026. OPB reports that Google 'has agreed to buy 50 megawatts of electricity', with the energy coming from 'Central Oregon's Newberry Volcano' to 'power three of its data centers in The Dalles', 'as early as 2030'. OPB says the companies did not disclose the sale price, and that Quaise 'will need to build a 10-mile transmission line' to a substation at La Pine. OPB reports that the federal entity owning about 75% of the region's transmission 'has only built one mile between 2020 and 2025'. Google's Lucia Tian, as quoted by OPB, said the risk 'includes higher costs'. Quaise's project page, dated 13 Apr 2026, lists Phase I at 50 MW, Phase II at 250 MW and Phase III at 1+ GW, and says Project Obsidian 'will be the first commercial deployment of millimeter wave drilling'. That page does not name the Phase I drilling method.

    Source published
    16 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    17 Nov 2026, 8:46 a.m. ET
    Location precision
    Region level (approximate)
  4. Illinois proposes keeping 11 gas and oil peaker plants open to May 2033, citing data-centre load growth

    On 16 November 2026 the Illinois Power Agency and Illinois EPA published a draft Resource Adequacy Mitigation Plan proposing to extend the CEJA zero-emissions deadlines for 11 eligible gas and oil units to 31 May 2033. The plan calls this "a defined bridge" and "not an indefinite extension"; coal units are excluded. The Illinois Commerce Commission's Integrated Resource Plan, Chapter 9, says Illinois "faces resource adequacy challenges that reflect broader regional and national trends, driven primarily by data center load growth." The draft plan's comment deadline is 15 January 2027, and the ICC makes the final decision. Why it matters to the watch (team's reading): a state plan to keep gas and oil peaker plants open to May 2033, driven by data-centre load growth (grid stress).

    Source published
    15 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    18 Nov 2026, 7:44 p.m. ET
    Location precision
    Region level (approximate)
  5. PJM proposes FERC ride-through rules for large computational loads of 50 MW or greater, after nearly 3.9 GW shifted to onsite generators in July

    On Monday 16 November 2026 PJM filed a proposal with FERC for new voltage and frequency ride-through requirements for current and future large computational loads. The filing defines a new category, Large Computational Load (LCL), as those "exceeding 50 MW or greater". Any new LCL must demonstrate compliance with these requirements "as a condition of interconnection and operation", with an effective date of Jan. 16, 2027 in the proposal. PJM says that on July 22 nearly 3.9 GW of data centers "unexpectedly transferred from utility power to their own onsite power generators", in response to a routine transmission disturbance. It was the largest such load transfer in PJM's history, with effects in the Dominion transmission zone and across the entire Eastern Interconnection. PJM says it already serves around 10 GW of existing LCL in its region and forecasts additions up to 30 GW by 2030.

    Source published
    15 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    16 Nov 2026, 9:58 p.m. ET
    Location precision
    City level
  6. Oregon PUC Order No. 26-443 adopts stipulation on PacifiCorp Schedule 401, "Service to New Large Energy Use Facilities"

    On 13 Nov 2026 the Public Utility Commission of Oregon entered Order No. 26-443 in docket UE463, adopting a stipulation on PacifiCorp's (dba Pacific Power) Schedule 401, "Service to New Large Energy Use Facilities". The order says the stipulation is "well suited to PacifiCorp's rural and dispersed service territory, adopting a direct contracting and direct assignment approach". Its introduction refers to "a 1-cent per kilowatt-hour surcharge". Paragraph 26 of the stipulation "imposes a 1 cent/kW charge on LEUFs over 100 MW". The order says the stipulation "ensures that large data centers will not impede the state's emissions goals, as required by the POWER Act". It describes LEUF agreements with a "maximum term of 30 years, inclusive of any ramp period", and renewals that "will be at least 10 years in length". The order implements HB 3546, the POWER Act, which directs the commission to allocate or directly assign the costs of serving large data centers. The order requires PacifiCorp to file new tariffs by 24 November 2026, to be effective 1 January 2027. Why it matters to the watch: the order adopts a stipulation setting the surcharge and contract terms for large data-centre loads.

    Source published
    12 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    17 Nov 2026, 10:47 a.m. ET
    Location precision
    Region level (approximate)
  7. Kentucky Power seeks approval for a 760 MW gas plant to serve a planned 1 GW TeraWulf data campus whose tenant is undisclosed

    Kentucky Power has asked the Kentucky Public Service Commission to approve a new 760 MW combined-cycle gas plant next to its Big Sandy unit in Louisa, plus a new substation in the EastPark Industrial Park area, to serve the Muskie Data Campus. The company's release dated 13 November 2026 says the campus is expected to support up to 1 gigawatt of contracted electric demand in phases by 2029, and that the project would provide more than $500 million in fixed-cost rate offsets and $100 million in winter bill credits for residential customers. WEKU reports on 16 November 2026 that the campus is a 1 GW project between Ashland and Grayson that TeraWulf is developing, that TeraWulf will pay for the transmission infrastructure and the new gas plant, and that TeraWulf has not disclosed which company will use the campus. The company says PSC decisions could come as early as mid-2027.

    Source published
    12 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    16 Nov 2026, 6:05 p.m. ET
    Location precision
    City level
  8. Data Center Power Demand Is Set to Surge, Raising New Climate Challenges: BloombergNEF

    On 11 Nov 2026 BloombergNEF published a release titled "Data Center Power Demand Is Set to Surge, Raising New Climate Challenges", describing a new report commissioned by Bloomberg Philanthropies. The release says BNEF "expects data center electricity demand to almost quadruple to 2,354 terawatt-hours by 2035", "equivalent to 7% of global electricity consumption". It says "BNEF has tracked 181GW of announced gas-fired generation proposed alongside data centers", with "more than 90% of which is in the US". If the planned on-site gas plants were built, they "would emit about 345 million metric tons of carbon dioxide equivalent a year". These are BNEF forecasts and estimates from its own modelling, company-stated, not measured emissions. The release says the report "reviews policies across 17 markets".

    Source published
    10 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    15 Nov 2026, 7:20 a.m. ET
    Location precision
    Location unknown
  9. San Francisco planners suggest studying a cap of about 50 MW on all data centres, citing transmission limits

    A San Francisco Planning Department report dated 10 November 2026, prepared under Ordinance 215-26's 45-day data-centre moratorium, says the city has about 1,000 MW of peak transmission capacity, 400 MW of it through the Transbay Cable. Peak use was about 900 MW in 2019 and about 800 MW in 2025, and it is rising by up to about 20 MW a year. The report says a new transmission line could take eight or more years once approved, and that no proposal to add capacity exists. It suggests studying 'an upper limit' on total data-centre capacity, 'e.g., 50 MW, with a specific value to be determined'. It says a 50 MW data centre would use as much power as over 25,000 new homes, and that San Francisco has no active applications for new stand-alone data centres. The moratorium expires on 30 November 2026 unless extended.

    Source published
    9 Nov 2026, 7:00 p.m. ET
    Event time
    Unknown
    Added to the Observatory
    16 Nov 2026, 5:05 p.m. ET
    Location precision
    City level

163 signals: 156 reviewed by editors, 7 published automatically after an AI check. 34 sources are monitored for new items; each is checked before it is published. This is a curated selection, not a complete record of global events. Signals without an established country are included here but belong to no region.